TLQ vs CLQ: What Temporary Labour Quarters Mean in Malaysia

If you house foreign or local workers in Malaysia, you will see two short forms: TLQ and CLQ. Both are ways to house workers, but they are meant for different time frames. This guide explains what each one means, how they differ, which approvals both need, and what happens when a TLQ period ends.

What does TLQ mean?

TLQ stands for Temporary Labour Quarters. In Malay it is penginapan pekerja secara jangka pendek (short-term worker accommodation) or penginapan pekerja sementara.

A TLQ is worker housing in an existing building that is allowed for a limited time only. The Ministry of Housing and Local Government (KPKT) set out the TLQ application procedure in its circular Pekeliling KSU KPKT Bil. 3 Tahun 2023, for a temporary period of 2024 to 2026.

The short-term route is not new. In 2021 KPKT split worker housing guidance into two tracks: urgent short-term housing during the pandemic, and better-planned long-term housing, which became the CLQ guideline.

What does CLQ mean?

CLQ stands for Centralised Labour Quarters (in Malay, penginapan pekerja berpusat). KPKT's planning guideline defines a CLQ as centralised or grouped housing for workers, foreign or local, in a dedicated area or building (permanent or semi-permanent), with basic and support facilities planned for the residents' comfort.

A CLQ is the long-term solution. It can be built by a private developer, an employer or a centralised accommodation developer, and can house workers from any sector. For more on CLQs, read CLQ meaning: what are centralised labour quarters?

TLQ vs CLQ at a glance

TLQ (Temporary Labour Quarters) CLQ (Centralised Labour Quarters)
Meant for The short term The long term
Building An existing building used for worker housing for a limited time A dedicated area or building for worker housing (permanent or semi-permanent)
Time limit Yes: KPKT's procedure covers 2024 to 2026; states set their own end dates No set end date
Local council approval Needed Needed
Certificate of Accommodation from JTKSM Needed Needed
Act 446 minimum standards Apply Apply

The same approvals apply to both

Whether the housing is a TLQ or a CLQ, the employer or provider needs two things:

  1. Local council approval. Under section 24H of Act 446, the local council confirms that a building is fit for worker accommodation. The council's approval comes first.
  2. A Certificate of Accommodation (Perakuan Penginapan) from the Department of Labour of Peninsular Malaysia (JTKSM), issued only after the council's approval. Act 446 applies in Peninsular Malaysia and the Federal Territory of Labuan.

Our guide to the Certificate of Accommodation explains the application step by step.

The same minimum standards apply inside

A temporary building gets no lighter rules. The Act 446 minimum standards are the same for a TLQ and a CLQ. For example:

Dormitory Non-dormitory
Sleeping space per worker 3.0 m² 3.6 m²
Bathroom and toilet 1 for every 15 workers 1 for every 6 workers

Each worker also needs their own bed, mattress, pillow, blanket and lockable cupboard, and the housing needs water, electricity, a rest area, a dining area and a kitchen.

What happens when a TLQ period ends?

The state and local council set the TLQ rules for their area. For example, Selangor's Selayang council takes short-term worker housing applications for existing homes, shophouses and shop offices. Penang has its own TLQ guideline, which says:

  • applications to the local council were accepted from 1 January 2024 to 31 December 2025 only, and the state does not consider new TLQ applications after that;
  • a TLQ approval lasts three years and ends on 31 December 2027;
  • when it ends, the building must return to its original use, and the workers living there must move to a CLQ;
  • the buildings allowed include existing strata homes, landed homes, commercial buildings and industrial buildings, each with its own conditions.

If your workers are in a TLQ today, check the end date your local council set, and plan where they will live next.

Why the government is pushing for CLQs

In June 2025, Human Resources Minister Steven Sim said CLQs and TLQs are meant to centralise the housing of foreign workers so that it does not affect local neighbourhoods. He also warned that the ministry would not hesitate to revoke the operating licences of CLQs and TLQs whose operators fail to comply with Act 446.

How WorkConnect runs its worker quarters

WorkConnect manages centralised labour quarters in Perak, in Tasek, Gopeng, Simpang Pulai, Bidor, Bercham and Meru, and in Cameron Highlands, Pahang. Locations in Chemor and Kampar are coming soon. See photos and facilities on our CLQ locations page.

Our labour quarter management follows four steps:

  1. Assessment and planning: we assess the current facilities or requirements and write a management plan for them.
  2. Implementation: our team takes over management, with systems for maintenance, security, administration and resident support.
  3. Monitoring and reporting: we give regular reports on performance, occupancy, maintenance and compliance.
  4. Continuous improvement: we use feedback and performance data to keep improving.

Moving workers out of a TLQ, or planning long-term housing? WhatsApp us on +60 14-302 2862 or see WorkConnect's worker quarters.


Sources

  1. Ministry of Housing and Local Government (KPKT), circulars list: Pekeliling KSU KPKT Bil. 3 Tahun 2023: Garis Panduan Perancangan Penginapan Pekerja Berpusat (CLQ) dan Prosedur Permohonan bagi Penyediaan Penginapan Pekerja Secara Jangka Pendek (TLQ) (read 26 November 2026). kpkt.gov.my
  2. KPKT and PLANMalaysia, Garis Panduan Perancangan Penginapan Pekerja Berpusat (CLQ), first edition, July 2021. jkt.kpkt.gov.my (PDF)
  3. Utusan Sarawak, KPKT sediakan garis panduan penginapan atasi isu tempat tinggal pekerja asing, tempatan (3 November 2023, in Malay). utusansarawak.com.my
  4. Penang State Government, Garis Panduan Perancangan Penginapan Pekerja Sementara (TLQ) di Kawasan Pihak Berkuasa Tempatan Negeri Pulau Pinang. penang.gov.my (PDF)
  5. Free Malaysia Today, P Pinang takkan timbang permohonan baharu TLQ mulai 2026 (18 November 2025, in Malay). freemalaysiatoday.com
  6. Majlis Perbandaran Selayang, Permohonan bagi Tujuan Penyediaan Penginapan Pekerja Jangka Pendek (application form, 2026). mps.gov.my (PDF)
  7. Department of Labour of Peninsular Malaysia, FAQ: Employees' Housing, Accommodation and Amenities. jtksm.gov.my
  8. Department of Labour of Peninsular Malaysia, Buku Panduan Penginapan Pekerja (April 2021). jtksm.mohr.gov.my (PDF)
  9. Malay Mail, After migrant protest, Human Resources Ministry warns of licence revocation for non-compliant worker hostels (22 June 2025). malaymail.com

This guide is general information, not legal advice. TLQ rules and end dates differ by state and local council; check with your local council and JTKSM before you house workers.

Prepared by Work Connect Group (M) Sdn Bhd.